Case study · Project management consultancy · Diriyah, Riyadh, Saudi Arabia

Diriyah Gyratory Tunnel cladding and finishing worksDiriyah · Riyadh · Saudi Arabia

We served as project management consultant to the specialist subcontractor joint venture (JV) across two consecutive phases. The JV supplied, fabricated and installed fire-rated wall, bulkhead and architectural finishing systems inside a live road tunnel at Diriyah, Riyadh, Saudi Arabia.

Phase 1 project value
SAR 72 million
Enhancement cladding works
Phase 2 project value
SAR 37 million
Tunnel extension works
Duration
About 1 year
Baselines: 8 months (Phase 1) + 3 months (Phase 2)
Our role
PMC
Project management consultant to the subcontractor JV
Completed tunnel wall finished in layered sand-coloured dune profiles with a lit cove line above, a site engineer and an operative carrying out final checks at the kerb.
The completed “dunes” wall finish: CNC-profiled fire-rated boards, a textured finish and LED cove lighting.
Phase 1

Diriyah Gyratory Tunnel Enhancement: cladding works

Main contractor
Salini Saudi Arabia
Subcontractor
Joint venture
Value
SAR 72 million
Baseline
8 months
Our role
Led project management for the JV, plus estimating, pricing and the award process
Phase 2

Diriyah Gyratory Tunnel Extension

Main contractor
Al Ayuni Investment & Contracting Company
Consultant
Jacobs
Subcontractor
Joint venture
Value
SAR 37 million
Baseline
3 months
Our role
Led project management for the JV, plus estimating, pricing and the award process

Tunnel cladding project in Diriyah, Saudi Arabia

This Diriyah Gyratory Tunnel case study brings together project management consultancy, tunnel cladding and finishing works, BIM coordination and structural steel fire protection in Riyadh, Saudi Arabia.

The tunnel walls and bulkheads needed a finish that was both fire-rated and architectural: a sculpted desert-dune surface lit by a continuous cove line. Under it sat a steel sub-frame with certified two-hour fire protection, built into a working tunnel crowded with MEP services. We ran the work as five integrated packages and coordinated the JV with the main contractor, the consultant and the specialist suppliers.

  • BIM modelling and as-built
  • Steel structure and intumescent coating
  • Calcium silicate boards: CNC cutting and grooving
  • Concrete plinth
  • Aluminium channel and LED cove lighting
01

Project planning and controls

We built the baseline programme on a critical-path chain in which each stage was released only when the one before it was ready. Contract and purchase-order close-out came first. Then BIM coordination and shop drawings, submittals and approvals, and fabrication of steel, boards and channels. Wall installation followed, then bulkhead, direct-fix and soffit works. Texture, paint, LED testing and handover came last.

Procurement followed the design milestones. Material orders and fabrication were released only against approved shop and fabrication drawings, so nothing was made to a design that might still change. Each submittal had a named originator, reviewer and target status in an approval matrix, which gave the main contractor and the consultant a live view of approvals against the programme.

Resourcing from measured production rates

We sized crews and durations from measured quantities and realistic daily output rates for each system. The Phase 2 planning basis:

Work itemQuantityPlanned rate
Wall system9,100 m²75 m²/day
Bulkhead system5,980 m²56.41 m²/day
Soffit painting11,397 m²300 m²/day
Direct-fix corners4,044 m²220 m²/day

The resource plan used segment-based crews, separate fabrication and installation streams, and QA/QC built into daily production. Running fabrication and installation in parallel let installation keep moving while the next batches were made.

Daily tracking and weekly control

We tracked progress daily against the BIM model, where every steel element was colour-coded as installed, delivered or not yet delivered. That gave everyone a single, visual record of what was on site and what was outstanding. Weekly coordination meetings with the main contractor and the consultant reviewed progress against the baseline. They also tracked the critical interface gates, such as MEP clearance before secondary steelwork, so emerging delays were raised early and corrective action agreed.

Wide view inside the tunnel during works, with scaffold towers against a partly finished wall and the cove-lit upper band already installed further along.
Segment-based execution. Finished, in-progress and not-yet-started bays running side by side along the tunnel.
02

Design development and value engineering

We set design development up for joint technical review by the main contractor and the consultant. Each deliverable went through a defined submittal route, with the consultant as reviewer and approval codes set as targets:

  • material and system data sheets, the method statement and design load calculations for the structures
  • a coordinated, clash-free BIM model
  • shop drawings, and fabrication drawings released with a fabrication inspection request
  • the intumescent loading table and system certificate
  • the inspection and test plan, and the mock-up approval record

The architectural intent was a sand-dune surface in six finishes, set out in a materials legend with specified textures and RAL colours over a precast concrete plinth. We turned that into production detail. Calcium silicate fire boards were CNC-cut and grooved to the dune profiles, joints were treated with a non-combustible putty and FRP tape to prevent cracking, and anti-carbonation paint was applied in the approved RAL colours. Bulkhead access panels were placed in the model so they cleared the MEP services.

Quality locked before production

A full mock-up of steel, board, joint, finish and lighting was built and inspected. Once the consultant and the main contractor signed it off, it became the acceptance benchmark for all production that followed. Production never ran ahead of an approved benchmark.

Coordinated wall elevation drawing showing six numbered dune-finish zones, a bulkhead access panel, fire board to the slab above and the precast concrete plinth at floor level.
Coordinated finishes elevation. Six finish zones, the bulkhead access panel and the precast plinth, resolved before boards were cut.
03

Delay management and schedule protection

In a live tunnel, the main schedule risks came from interfaces outside the JV's control. We identified them at the start, gave each an owner and a mitigation, and tracked them every week. When an interface slipped, the weekly review measured its effect on the affected activity against the baseline, so corrective action and any entitlement could be raised with the main contractor while the facts were current.

Interface riskActivity or milestone affectedOwnerControl we put in placeSeverity
MEP clearances not releasedSecondary steel beamsSharedMEP clearance made a formal gate before beam installation and tracked weeklyHigh
Late submittal and approval cyclesFabrication releaseSharedApproval matrix with agreed review periodsHigh
Fire-protection certification not matching section sizesSteel coating and releaseJVSystem certificate checked against the project's range of section factors (Hp/A)High
Concrete out of tolerance against set-outAnchoring and frame installationMain contractorAs-built scan validated the datum before any steel was mountedMedium
Damage to finished surfacesTexture, paint and handoverJVProtect-and-sequence control, with texture applied lastMedium
Access and lifting in a live tunnelAll installationJVPermits to work, access platforms and lifting plansMedium
04

BIM coordination and as-built delivery

The model came first: no steel was fabricated until it had been validated against the tunnel as actually built, and the model carried through to as-built documentation at handover. We oversaw a five-step model workflow:

  1. As-built scan of the concrete. We scanned the completed tunnel concrete into an as-built model and integrated it with all disciplines, so set-out was based on real geometry rather than design tolerances.
  2. Steel modelling in Tekla. We modelled the wall and bulkhead steel in Tekla Structures and linked it to Revit and Navisworks for cross-discipline coordination.
  3. Clash detection and MEP coordination. We coordinated steel members and access-panel locations with the MEP and architectural models and resolved clashes before fabrication.
  4. Shop drawings. Once coordination was complete, we issued shop drawings for the consultant's review and approval.
  5. Fabrication drawings. We extracted fabrication drawings directly from the approved Tekla model and released them to the fabricator.

Each tool and its purpose

Autodesk RevitCross-discipline coordination: the Tekla steel model was linked to Revit so steel, architecture and the as-built tunnel geometry were reviewed together.
Tekla StructuresSteel detailing: shop and fabrication drawings came straight from the model. The same model carried the installation tracker, with every member coloured as installed, delivered or not delivered.
Autodesk NavisworksFederated clash detection between steel, access panels, MEP and architecture. A clash-free coordinated model was a formal submittal reviewed by the consultant.
Tekla Structures 3D model of the tunnel wall steel framing along numbered gridlines 24 to 30, with members coloured green, blue and red to show installation status.
Tekla model as installation tracker. Green installed, blue delivered, red not yet delivered, by gridline.
05

Structural steel and fire protection

We managed the structural steel subcontractor against one fabrication and QA standard, applied to the wall and bulkhead steel alike, from the fabrication shop to final torque.

Fabrication and third-party inspection

  • All components were fabricated strictly to approved fabrication drawings.
  • Dimensional checks, weld inspection and non-destructive testing (NDT) were carried out and recorded for every assembly. Visual and NDT inspection by a third party was a witness point in the inspection and test plan, measured against the approved welding procedure specification.
  • Each inspection report traced the material back to its mill certificate, batch number and heat number.

Site installation

  1. Anchoring. We set out anchors to surveyed coordinates: an approved chemical anchor system on the walls, and mechanical anchors on the bulkheads.
  2. Columns and frames. We fixed columns and frames to the structure and held them for pull-out testing. Gaps were grouted where needed.
  3. MEP clearance gate. Secondary beams were installed only after MEP clearance had been formally given.
  4. Secondary beams and torque. Beams were bolted with the specified bolt grade and tensioned to the design torque. Every torque test was recorded, and torque was a hold point.

Intumescent coating: calculating and managing the loading tables

The steelwork needed a 120-minute (two-hour) fire rating. The protection system was a water-based intumescent coating applied over prepared and primed steel and finished with a white top coat.

The required dry-film thickness (DFT) is different for every steel section. We determined it like this:

  1. Calculate the section factor. For each section we calculated the section factor (Hp/A): the heated perimeter divided by the cross-sectional area. Thin, slender sections heat faster, so they have a higher Hp/A and need more coating.
  2. Read the required DFT. For each section factor we read the required DFT for a 120-minute rating from the coating supplier's certified loading table, which gave a calculated DFT of 1,800 µm.
  3. Check against the certificate. We confirmed that the project's full range of Hp/A values fell within the system certificate, and submitted the loading table and certificate to the consultant for approval before any coating started.
  4. Verify every coat. A third-party inspector measured the DFT of each coat with a calibrated Elcometer gauge. This was a hold point: steel was not released until readings met the approved loading table.
Operative in a protective suit spray-coating rows of fabricated grey steel bulkhead frames supported on stands inside a fabrication workshop.
Shop coating. Fire-protection coating sprayed onto fabricated bulkhead frames in the workshop, before delivery.
Long tunnel wall lined with white-coated vertical steel columns anchored to the concrete, with red fire-main piping and overhead services above.
Site installation. Coated wall columns anchored and aligned along the tunnel before the secondary beams went in.
Inspector holding a digital coating-thickness gauge with its probe pressed against a white intumescent-coated steel member to measure dry-film thickness.
DFT inspection. Coating thickness checked with a calibrated gauge at every coat, against the approved loading table.
06

Subcontracts, pricing and resources

On both phases our role began before the contract was signed. We led the JV's estimating, pricing and award process. Quantities were measured for each system, and durations and crew sizes were built up from production rates, so the price, the programme and the resource plan all came from one set of numbers.

After award, we prepared the subcontracts and purchase orders across the work packages, setting delivery dates and prices in each against the project estimate and the critical path. Contract and purchase-order close-out was the first activity on the programme, so every supplier was committed before the work that depended on them started.

On site, we managed manpower, equipment and engineering staff by segment. Each segment had its own crew, fabrication ran separately from installation, and access equipment (mobile elevating work platforms and scaffold towers) was planned with lifting plans and permits to work. Each month we prepared an inspection-ready progress package so the main contractor and the consultant could certify the interim payment application against inspection records rather than estimates.

Installation crew in hard hats and hi-vis vests working from a multi-level scaffold to fix fire boards to the steel sub-frame, with stacked boards on pallets in the foreground.
Segment crews. A board-installation crew working from scaffold access, with materials staged at the work face.
Outcomes

What the project delivered

  • Two phases, one management team. Project management across SAR 72 million and SAR 37 million phases, for two different main contractors.
  • A fire-rated, architectural tunnel finish. Steel sub-frames with 120-minute intumescent protection, CNC-profiled fire boards and LED cove lighting, forming a continuous dune-themed surface.
  • Model-led delivery. An as-built scan, a Tekla steel model coordinated in Revit and Navisworks, and fabrication drawings issued from the approved model.
  • Traceable quality. Third-party NDT and DFT inspection, pull-out and torque tests as hold points, and full mill-certificate traceability.
  • Two programmes, one method. An 8-month Phase 1 baseline and a 3-month Phase 2 baseline, both run on the same approvals-first, segment-by-segment model.
Finished tunnel wall panel with a smooth curved white board surface, a warm ochre upper band and a continuous LED cove line tracing the curve between them.
Cove lighting traces the dune profile along the joint between the board finish and the upper band.